How many yards of concrete for a slab? (10×10 to 30×40)
A 4 in thick concrete slab covers about 81 ft² per cubic yard before waste. That means a 10×10 patio needs 1.36 yd³ (62 bags of 80 lb), a 20×20 two-car garage needs 5.43 yd³, and a 30×40 shop slab needs 16.3 yd³ at 4 in or 24.44 yd³ at 6 in (including 10% waste).
1. How to work out cubic yards for any slab
Convert thickness from inches to feet (4 in = 0.333 ft; 6 in = 0.5 ft), multiply length × width × thickness to get cubic feet, then divide by 27 for cubic yards. Add 10% waste for uneven subgrades, form deflection and concrete left in the chute or wheelbarrow:
Cubic yards = (length × width × thickness ÷ 12) ÷ 27 × 1.10
On a 30 × 40 ft (1,200 ft²) slab at 6 in thick, exact volume is 1,200 × 0.5 ÷ 27 = 22.22 yd³. Adding 10% brings your order plan to 24.44 yd³ — about 2½ full ready-mix trucks.
Open the 30 × 40 × 6 in slab presetCompare cubic yards, 80/60/40 lb bags and ready-mix truck cost
2. Common slab yardage and 80 lb bag chart
Built directly from the Concrete Calculator. One cubic yard equals 45 bags of 80 lb QUIKRETE Concrete Mix (0.60 ft³ each); the bag columns include 10% waste.
| Slab size | Area | 4 in exact | 4 in + 10% | 4 in (80 lb bags) | 6 in + 10% | 6 in (80 lb bags) |
|---|---|---|---|---|---|---|
| 10 × 10 ft | 100 ft² | 1.23 yd³ | 1.36 yd³ | 62 | 2.04 yd³ | 92 |
| 12 × 12 ft | 144 ft² | 1.78 yd³ | 1.96 yd³ | 88 | 2.93 yd³ | 132 |
| 12 × 16 ft | 192 ft² | 2.37 yd³ | 2.61 yd³ | 118 | 3.91 yd³ | 176 |
| 16 × 20 ft | 320 ft² | 3.95 yd³ | 4.35 yd³ | 196 | 6.52 yd³ | 294 |
| 20 × 20 ft | 400 ft² | 4.94 yd³ | 5.43 yd³ | 245 | 8.15 yd³ | 367 |
| 24 × 24 ft | 576 ft² | 7.11 yd³ | 7.82 yd³ | 352 | 11.73 yd³ | 528 |
| 24 × 30 ft | 720 ft² | 8.89 yd³ | 9.78 yd³ | 440 | 14.67 yd³ | 660 |
| 30 × 40 ft | 1,200 ft² | 14.81 yd³ | 16.3 yd³ | 734 | 24.44 yd³ | 1,100 |
3. DIY bags vs. ready-mix truck: where is the cutoff?
Bags make sense for small pads, footings and post holes under roughly 1 to 1.5 yd³ (about 45–68 bags of 80 lb). Above 1.5 yd³, even if a ready-mix supplier charges a short-load fee on orders under 3–5 yd³, hauling and mixing 5,000+ lb of bagged mix by hand takes a full crew and risks cold joints between batches.
Enter your local price per bag, ready-mix price per cubic yard and delivery fee directly in the 10 × 10 cost comparison preset to see the material break-even for your pour.
Remember that concrete slabs also sit on a compacted gravel subbase (estimate stone tonnage with the Gravel Calculator) and need control joints spaced according to slab thickness.
A few useful answers.
How many yards of concrete for a 30×40 slab?
At 4 in thick, a 30×40 slab holds 14.81 yd³ exact or 16.3 yd³ with 10% waste. At 6 in thick, it holds 22.22 yd³ exact or 24.44 yd³ with 10% waste. Thickened edges or footings add extra volume.
How many yards of concrete for a 20×20 garage slab?
A 20×20 slab at 4 in needs 4.94 yd³ exact (5.43 yd³ with 10% waste). At 6 in thick for heavier vehicles, plan on 7.41 yd³ exact or 8.15 yd³ with 10% waste.
How many 80 lb bags of concrete equal 1 cubic yard?
One cubic yard is 27 ft³. At 0.60 ft³ per 80 lb bag, one cubic yard takes 45 bags before waste, or about 50 bags with 10% waste.
Should I order 4 in or 6 in thickness?
Walkways and light patios commonly use 4 in slabs, while driveways, workshops and heavy equipment pads often call for 5–6 in or thickened edges. Always follow local building code and structural plans.
Sources
- QUIKRETE: Concrete Mix No. 1101 data sheet — 0.60 ft³ yield per 80 lb bag.
- Portland Cement Association: Slabs on Grade — subgrade preparation, thickness and control-joint spacing guidance (typically 24–36× slab thickness).
Thickened monolithic edges, rebar, wire mesh, vapor barriers and forms are not included in flat-slab volume estimates.